01 · Start with a decision
When two lines make the same product, does the faster one also use less energy per good part? A small batch may use fewer kWh overall, yet warm-up can account for a large share of its unit cost.
You do not always need to replace a PLC, renew the SCADA or implement a complete factory management system. Review existing measurements and production data first. If they are insufficient, instrumenting one specific point may be enough. Feasibility and cost depend on the installation.
02 · Define what is included
Set the measurement boundary: one machine, cell or complete line. Record whether it includes peripherals, cooling, extraction and other auxiliaries. Assigning the whole building’s consumption to one machine would be misleading.
Define batch start and end. Include preparation, warm-up, production and cleaning, or track those phases separately. Apply consistent rules and explicitly allocate consumption between batches.
Choose whether the denominator is total parts or good parts. The latter reflects rejects: the energy used to make defective parts is still part of the process.
03 · The minimum data you need
| Data | Purpose | Possible source |
|---|---|---|
| Starting and ending energy, in kWh | Consumption over the period | Energy meter or analyser |
| Batch start, end and ID | Match energy and output | PLC, production order or operator record |
| Total and good parts | Calculate indicators and rejects | Production counter and quality records |
| Product reference | Compare equivalent batches | Order or machine selection |
| Applicable price, in €/kWh | Convert consumption into cost | Contract and billing data |
Clocks and measurement windows must agree. Do not mix one shift’s consumption with another shift’s output. Flag and review incomplete data following meter resets or communication failures before reporting.
04 · Use existing equipment
Review panel analysers, submeters, drives, PLCs and SCADA. Some provide cumulative energy and communications; others show only power or an internal estimate. Check model, units, accuracy and measurement scope.
kW and kWh are different. kW expresses instantaneous power; kWh expresses energy over an interval. Nameplate power multiplied by hours is not the actual consumption of a machine with varying loads.
Measured active power can estimate energy by integrating samples: sum kW × hours for each interval. Sampling frequency and data gaps affect the result. A suitable cumulative energy meter simplifies calculation using the difference between readings.
If measurement is missing, assess adding a meter to the chosen circuit. Qualified professionals should perform electrical installation and checks. Measure the point that answers the question without replacing useful equipment.
05 · Worked example per batch and good part
Assume one product, a dedicated line meter and a constant price throughout the batch. The window includes preparation and production. These figures are illustrative, not customer measurements or a market tariff.
| Item | Value |
|---|---|
| Starting reading | 12,450 kWh |
| Ending reading | 12,570 kWh |
| Parts produced | 1,000 |
| Good parts | 950 |
| Energy price used | €0.15/kWh |
Batch consumption = ending − starting reading
12,570 − 12,450 = 120 kWh.
Batch electricity cost = consumption × price
120 × 0.15 = €18.00.
Energy per good part = 120 ÷ 950 = 0.1263 kWh
Cost per good part = 18 ÷ 950 = €0.01895, approximately 1.90 euro cents.
Dividing by all 1,000 produced parts gives €0.018 per part. That is a different indicator: its denominator does not reflect the 50 unsaleable units. Keep both if useful, but label them clearly.
06 · Choose the appropriate price
If prices vary by period or hour, calculate each interval and add them: batch cost = sum of interval energy × applicable price. For 80 kWh at €0.12/kWh and 40 kWh at €0.20/kWh: 9.60 + 8.00 = €17.60.
This covers the variable components included in your price, rather than automatically allocating the entire bill. Contracted capacity, demand overruns, reactive energy, rentals and taxes need specific treatment if included. Document the scope and shared-cost allocation.
To compare efficiency, look first at kWh per good part. Cost can fall solely because prices fall. Dividing the whole monthly bill by monthly output gives an average accounting cost for the chosen scope, rather than measured consumption per batch.
07 · Deal with shared utilities
A compressor, chiller or extraction system may serve several lines. If the machine meter excludes these utilities, the previous result excludes them too.
Measure each branch or apply a documented allocation, such as measured flow or operating time where reasonable. Allocating by hours assumes certain load conditions; do not present it as direct measurement unless those assumptions have been checked.
Separate measured energy from allocated energy. Avoid adding compressor consumption again if the overall meter already includes it. Do not convert compressed-air volume directly to kWh without a justified conversion relationship.
08 · Interpret the result
Compare the same product within equivalent boundaries and known conditions. Batch size, rejects, warm-up, speed, temperature and equipment condition can affect the result.
Another comparable batch using 110 kWh for 950 good parts would yield 0.1158 kWh per good part, 8.3% lower. This is a reason to investigate, rather than sufficient evidence of savings attributable to an intervention.
Validate the data, repeat observations over representative periods and review relevant variables. A single ratio does not replace process analysis. With no good parts, unit cost cannot be calculated: report consumption and the incident, rather than zero cost.
09 · A report that supports decisions
A clear table can be enough: date, line, product, start and end, kWh, good parts, reject rate, kWh per good part and cost per batch. Include pricing rules, phases and data quality.
Flag incomplete batches and allow access to source records. Meter resets and unvalidated output should be visible. Automation should reduce manual work without hiding exceptions.
Alerts should compare equivalent references. One universal threshold is inappropriate for different products and conditions.
10 · A focused first project
- Choose a question: product cost, line comparison or batch-size effects.
- Review sources: existing meter, PLC records and batch identification.
- Define rules: boundary, phases, good parts, price and auxiliaries.
- Validate a sample: compare meter readings and output with plant records.
- Observe enough variation: record representative batches and conditions before expanding.
There is no universal pilot duration. Continuous processes, seasonal production and frequent product changes require different periods. The result should support a specific decision even before the whole factory is covered.
11 · Common questions
Can I start without connecting the PLC?
Yes. Meter readings and reliable batch records let you validate the method manually. Connecting sources reduces effort and enables more frequent monitoring.
Must I replace the SCADA?
Not necessarily. Existing data may support a complementary report. Check communications, licences, permissions and capacity first.
Will any meter work?
No. It must cover the correct circuit and measure the required quantity with adequate resolution and accuracy. A number displayed on a screen is not automatically suitable.
How much will I save?
Measurement helps identify differences and verify changes, but guarantees no savings percentage. Opportunities depend on findings and feasible actions.
12 · A cost you can explain
The first goal is a number you can explain: energy included, batch, good output and price applied. This gives you a basis for comparisons, investigating deviations and assessing improvements.
At Rosanes Tech we can assess how to collect data from existing meters, PLCs and systems, relate it to production and generate reports suited to your process. Any missing measurement is defined before expanding the project.